We will be carrying out network maintenance during the night of 15-16 January 2011.  The purpose of this work is part of a multiphase plan to remove the legacy nework topology and migrate to a more stable, scalable, and efficent hierarchical model in Paris. 

 

In this phase, the activity will only involve the interconnections beween the core and aggregation network elements at our datacenter in St. Denis.

 

This activity will have several minor impacts on connectivity for various Gandi services in Paris throughout the maintenance window, each up to five minutes as the migrations are performed in the various sections of the network, but no significant outages are expected.

 

We have scheduled this maintenance window from 02:00 CET (01:00 GMT) to 08:30 CET (07:30 GMT) on 16 January during the period of lowest impact to customers.

 

We will schedule follow-on maintenance activity over the coming weeks for the rest of the network migrations, to include activities at Telehouse as well as a number of services in particular, and we will of course endeavour to keep any disruption to a minimum.